On this project, thermal insulation was installed in two layers: the first layer placed between the ‘standing seam’ ribs and the second layer laid continuously to eliminate thermal bridges and interruptions in insulation.

After insulation, the waterproofing membrane was applied and mechanically anchored to the primary roof structure through the insulation layers.

This project required significant expertise in shaping sloped insulation sections and the final application of the PVC waterproofing membrane.

The total installed waterproofing area is approximately 300 m².

Photos below showcase the craftsmanship, precision, and quality achieved by our experienced waterproofing team.