At the ‘Coca Cola’ production complex in Zemun, waterproofing was applied to new ventilation ducts.
Following a request from the mechanical installation contractor, waterproofing was planned for the new sheet metal ducts.
Key phases had to be coordinated:
- Roof cutouts
- Ventilation duct installation
- Waterproofing application
The existing roof has an EPDM membrane, which is incompatible with PVC/FPO membranes – posing an added challenge.
The ducts were waterproofed using Sikalastic 641 liquid polyurethane membrane and reinforced with Sikaplan 15G PVC membrane.
Application of liquid membrane required optimal weather: no rain, dew, or low temperatures.