- 09.09.2021.
- -
On the residential building in Ruma, the existing waterproofing was repaired by applying new waterproofing to address leaks into the building.
The ‘Sikaplan U15‘ waterproofing was used. A hydro-test was also conducted by filling the waterproofed area with water to check for leaks.
For the hydro-test, the water must remain for at least 24-48 hours, but in this case, the water was left for 10 days until the investor was assured with the quality of the work.
The total hydro-insulated area is approximately P=39m².
Attached are photographs taken after the completion of the work and photos from the hydro-test.