- 15.04.2019.
- -
The storage facility “Ball Packaging B2” is a completely new construction as an investment, i.e. an addition of a new object as part of the production circle of the “Ball Packaging” can factory.
Works were carried out on the installation of thermal insulation and waterproofing membrane on the roof, and the special feature of this roof is the installation of thermal insulation in slope, so-called “tapered insulation”, for the purpose of reducing water to drains in horizontal bays with an approximate square footage of P=1,300 m2.
Service installation of thermal insulation and waterproofing “Sikaplan 15G” with a total area of P=8,500 m2 was carried out on this project.