- 17.12.2020.
- -
Within the ‘Robert Bosch‘ production complex in Šimanovci, the floor in the testing room was repaired.
Water was leaking through the ceramic tiles, so a temporary installation of PVC waterproofing was carried out until the entire floor of the room could be repaired.
The ‘Sikaplan 15G‘ membrane was installed and ‘Walkway-20‘ pathways were used for protection because testing machines for hydro-testing parts produced in the factory are placed on top of the waterproofing.
Attached are photographs taken during and after the completion of the work.